Hebron Avenue Pavement Rehabilitation

This is a 100% Grant-funded project that included rehabilitation of the pavement structure on Hebron Avenue between Main Street and Sycamore Street.  This project provides for new pavement structure for all town-owned portions of Hebron Avenue that are not being reconstructed as part of either of the two roundabout project.  Full depth pavement construction with new granite curbing will be completed from 400 feet east of Main Street to the House Street intersection, with remaining areas being milled and paved.  This project will start construction in the Spring of 2018 and will run concurrently with the House Street / Hebron Avenue Roundabout Project.  Substantial completion is anticipated in the Fall of 2018.